A document issued by the Office of the Municipal Engineer (OME)/Office of the Building Official (OBO), in accordance with the format outlined in NBCDO Memorandum Circular 01, series of 2020. This document advises owners/applicants to proceed with various construction activities such as construction, installation, addition, alteration, renovation, conversion, repair, moving, demolition, or other related work on a specific project/building/structure or portions thereof. Such activities are permitted once the accompanying principal plans, specifications, and other pertinent documents submitted with the application are deemed satisfactory and in substantial conformity with the National Building Code of the Philippines (NBCP) and its Implementing Rules and Regulations.
Step 1 of 4
APPLICATION FOR BUILDING PERMIT (ALL BUILDINGS / STRUCTURE OF MORE THAN TWO-STOREY, SPECIAL STRUCTURES UNDERGROUND STRUCTURES AND WINDOWLESS BUILDING)
External Services
Details
|
OFFICE/UNIT |
OFFICE OF THE MUNICIPAL ENGINEER |
|
CLASSIFICATION |
Highly Technical |
|
TYPE OF TRANSACTION |
G2C – Government to Citizens G2B – Government to Business G2G – Government to Government |
|
WHO MAY AVAIL |
Any person, firm or corporation including any government agencies or instrumentality who planned to erect, repair/renovate, convert any building or structure or cause the same to be done within the municipality. |
|
|
Construction / erection / addition / alteration / renovation / repair / legalization of the following Highly Technical Type of Project Activity / Structures:
All other transactions not expressly falling under either ‘Complex’ or ‘Highly Technical’ shall, for the purpose of these Guidelines, be considered as ‘Simple’ consistent with the mandate of RA No. 11032. |
Requirements
| # | Checklist & Where to Secure | ||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
||||||||||||||||||||||||||||
| 2 |
|
||||||||||||||||||||||||||||
| 3 |
|
||||||||||||||||||||||||||||
| 4 |
|
||||||||||||||||||||||||||||
5 STEPS
|
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME |
PERSON RESPONSIBLE |
|
1.1 Receive and verify the completeness of application documents in accordance with the provided checklist of requirements. (If complete, issue acknowledgement receipt)
1.2 Encode received application and documents.
1.3 Site Inspection, check condition of the lot and its boundaries, check adopted setback, check status of construction. And prepare inspection report.
1.4 Evaluation of building plans and other supporting documents. Land Use and Zoning, Line and Grade, Architectural, Structural, Electrical, Mechanical, Sanitary, Plumbing, and Electronics
1.5 Prepare order of payment
1.6 Sign and approve order of payment. |
None
None
None
None
None
None
|
2 hours
1 hour
1 day
17 days
4 hours
1 hour |
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
2. Issue approved order of payment |
None
|
5 minutes |
Engr. Ralph Jayson A. Loto Engineering Office |
|
3. Received payment and issue Official Receipt (O.R.) |
Refer to NBCP (PD1096) prescribed Schedule of Fees |
20 minutes |
Cashier Municipal Treasurer’s Office |
|
4.1 Check / Record O.R. Number, and assign Bldg. Permit Number, Architectural Permit Number, Civil/Structural Permit Number, Electrical Permit Number, Mechanical Permit Number, Sanitary Permit Number Plumbing Permit Number, Electronics Permit Number, Encode on permit forms, stamp plans and permits, and Segregation of plans and documents for applicant and office copy.
4.2 Signed and approved the Building and Ancillary plans and Permit |
None
None
|
4 hours
3 hours
|
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
5. Release approved Building and Ancillary plans and permit and checklist to owner or applicant. |
None
|
35 minutes |
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
|
TOTAL |
Refer to NBCP (PD1096) prescribed Schedule of Fees |
20 DAYS |
|