APPLICATION FOR DEMOLITION PERMIT (ANY TYPE OF OCCUPANCY / USE OF MORE THAN 200 SQM AND MORE THAN TWO-STOREY IN HEIGHT)
External Services
Demolition Permit, An Accessory Permit issued by the Building Official for construction activities initiated before or during the application/processing of Building Permits. This document authorizes owners/applicants to proceed with the demolition of a specific project/building/structure or portions thereof once the accompanying principal plans, specifications, and other pertinent documents with the application are deemed satisfactory and substantially conform to the National Building Code of the Philippines (NBCP) and its Implementing Rules and Regulations.
Certificate of Occupancy, a document issued by the Building Official, in adherence to the format specified in NBCDO Memorandum Circular 01, series of 2020, which attests that the building/structure has been finalized and is suitable for occupation/use as per the approved purpose.
Details
|
OFFICE/UNIT |
OFFICE OF THE MUNICIPAL ENGINEER |
|
CLASSIFICATION |
Complex |
|
TYPE OF TRANSACTION |
G2C – Government to Citizens G2B – Government to Business G2G – Government to Government |
|
WHO MAY AVAIL |
The owner/s of newly constructed/renovate/repaired building or structure within the municipality. |
|
|
Any type of occupancy / use with area of more than two hundred (200) square meters and more than two storey in height. |
Requirements
| # | Checklist & Where to Secure | ||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
5 STEPS
|
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME |
PERSON RESPONSIBLE |
|
1. Submit duly accomplished application forms and supporting documents and claim acknowledgement receipt (stub). |
1.1 Receive and verify the completeness of application documents in accordance with the provided checklist of requirements. (If complete, issue acknowledgement receipt)
1.2 Encode received application and documents.
1.3 Inspect location of project site and prepare inspection report
1.4 Evaluation of methodology for demolition and technical requirements
1.5 Prepare Order of Payment
1.6 Sign and approve Order of Payment |
None
None
None
None
Refer to NBC (PD1096) prescribed Schedule of Fees
None
|
40 minutes
10 minutes
4.5 days
2 days
1 hour
1 hour
|
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto Engineering Off.
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
2. Claim Order of Payment |
2. Issue Order of Payment |
None |
10 minutes |
Engr. Ralph Jayson A. Loto Engineering Office |
|
3. Pay Permit fees |
3. Received payment & issue official receipt |
None |
15 minutes |
Cashier Municipal Treasurer’s Office |
|
4. Present O.R. to OBO |
4.1 Check and Record O.R. No. and assign demolition permit number, encode on permit forms, stamp plans and permits. Segregation of plans and documents for applicant and office copy.
4.2 Approve Demolition Permit and plans. |
None
None |
30 minutes
10 minutes |
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
5. Claim approved Demolition Permit |
5. Release approved Demolition Permit and plans. |
None |
5 minutes |
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
|
TOTAL |
Refer to NBCP (PD1096) prescribed Schedule of Fees |
7 DAYS |
|